Brock Trail 2018 Construction Projects

The above picture can be clicked to expand full-size, and downloaded for reference. It shows the projects currently underway on the Brock Trail. Heavy equipment and other activity on the under-construction segments may limit passage. The two segments in particular where this is true include:

Perth to Stewart – expected to be completed by early June, the work here includes removal of a utility pole and its support cables near the Perth Street end; additional fill, drainage and grading of the central part of the segment and the short connector to Front St; paving; and a pedestrian crossover on Perth St.

Laurier to Centennial – construction is likely to continue into early summer on this segment. Work includes:

  • bridge abutments, bridge installation, and connector trail to Aspen Dr
  • paving of the trail from end to end
  • a pedestrian crossover on Centennial road to the parking lot at the Mac Johnson Wildlife Area canoe launch
  • at the Laurier Blvd end, a paved and curb-separated trail connection on the road shoulder to the intersection with Bridlewood; a pedestrian crosswalk across Bridlewood; a pedestrian crossover across Laurier Blvd;
  • a new separated trail segment from the south side of Laurier at the crossover to the Fieldhouse and then across the existing bridge to connect with the existing Brock Trail segment.

When the Laurier to Centennial segment is completed, the Brock Trail will provide an off-road active transportation corridor from the Mac Johnson Wildlife Area all the way to downtown and waterfront, where it connects with the 3,000+ km Great Lakes Waterfront Trail network spanning Ontario.

 

Author: Alan Medcalf

Alan is a post-corporate, volunteer, community builder living in Brockville, Ontario. He seeks to create sustainable lifestyle advantage for the community by creating opportunities for more people to choose to walk and to ride bikes. He promotes the health, social, environmental and economic benefits of active mobility.